MAINE PUBLIC • June 10, 2020
Opponents of Central Maine Power's proposed powerline through the state's western woods are lining up to formally challenge the Department of Environmental Protection's (DEP) recent permit for the project. On Tuesday, an array of individuals and conservation organizations, plus the potential host towns of Caratunk and west Forks Plantation, called for a stay of any physical work on the project. They say to avoid irreversible environmental damage, work should be on-hold until federal permits are issued and voters weigh in on a statewide referendum in November. And Wednesday, the state's largest environmental advocacy organization, the Natural Resources Council of Maine (NRCM), filed a formal appeal of the DEP permit. CMP called the moves "baseless."